News

Back

Latest News

Judicial Deference to Arbitration Award Upheld in Delhi High Court

Background

The case of M/S Cobra Instalaciones Y Servicios, S.A., and Shyam Indus Power Solution Pvt Ltd. (jointly referred to as "the J.V. Company") versus Haryana Vidyut Prasaran Nigam Ltd. (HVPNL) revolves around a contractual dispute related to the delay in completing Project G09. The J.V. Company was contracted by HVPNL to complete several infrastructure projects, including Project G09, which involved setting up three substations and six bays. The original completion date was set for June 27, 2013. However, due to delays, HVPNL imposed liquidated damages (L.D.) on the J.V. Company. The J.V. Company contested this imposition, leading to arbitration and subsequent court proceedings.

 

Court Proceedings and Judgements

The appeal was heard by Hon'ble Mr Justice Rajiv Shakdher and Hon'ble Mr Justice Amit Bansal in the High Court of Delhi. The bench reserved its judgment on February 1, 2024, and pronounced it on April 10, 2024. The case number is FAO(OS) (COMM) 195/2022 & CMAPPL. 32865/2022. The dispute focused on the quantum of L.D. imposed and whether HVPNL had appropriately justified the damages.

 

Key Facts

Arbitration and Initial Award:

An arbitral award dated July 29, 2020, ordered a refund of 50% of the L.D. imposed by HVPNL, amounting to Rs. 3,62,50,755/-.

The arbitrator awarded interest at 13% per annum from the date of L.D. deduction until the institution of the Statement of Claims (SOC) and future interest at 9% per annum from the award date until payment.

 

Single Judge's Reversal:

The Single Judge of the High Court reversed the arbitral award concerning L.D. on April 25, 2022, prompting the J.V. Company to appeal the decision.

 

Project Details:

Project G09 involved the construction of three substations and six bays, originally scheduled for completion by June 27, 2013. Delays occurred, which the J.V. Company attributed to factors beyond their control, including issues with the contractor responsible for the feeding/transmission lines.

 

Contention Points:

The J.V. Company argued that HVPNL had not incurred actual losses warranting the imposed L.D. and that the delays were due to external factors beyond their control.

HVPNL maintained that the delays justified the L.D. as per the contractual terms, emphasizing their right to impose such damages under the agreement.

 

Arguments and Evidence

The J.V. Company's Position:

The J.V. Company highlighted that the delay in Project G09 was primarily due to the inefficiencies and delays caused by the third-party contractor responsible for the feeding/transmission lines.

They argued that HVPNL had not suffered actual monetary losses to justify the full amount of L.D. imposed. The J.V. Company pointed to other projects where similar delays had occurred but were met with partial or full refunds of L.D., showcasing inconsistency in HVPNL's application of L.D.

 

HVPNL's Position:

HVPNL defended the imposition of L.D. by stating that the J.V. Company was contractually obligated to complete the project within the stipulated time frame, and the delays impacted the project's timely completion, justifying the L.D.

HVPNL argued that the arbitrator had overstepped by reducing the L.D. without a precise quantification of losses, contrary to the contract's stipulations.

 

Court's Analysis and Decision

Assessment of Losses:

The court noted that in similar projects (G14A, G17, G19A, and G19B), HVPNL had either refunded or partially retained L.D. based on specific circumstances, highlighting inconsistency in their approach.

The arbitrator's decision to reduce L.D. by 50% was based on the assessment that HVPNL had not provided a precise quantification of the losses incurred due to the delay in Project G09. This assessment was deemed reasonable by the court, considering the lack of detailed evidence from HVPNL to justify the full L.D. amount.

 

Public Benefit Consideration:

The arbitrator acknowledged that Project G09 served the public interest, which factored into the decision to reduce the L.D. The court agreed with this balanced approach, emphasizing the importance of considering the broader public interest in such infrastructure projects.

 

Judicial Deference to Arbitration:

The High Court reaffirmed the arbitrator's stance that HVPNL had not sufficiently quantified the losses but reversed the Single Judge's decision, restoring the 50% L.D. refund to the J.V. Company. The decision underscored the importance of precise loss quantification in enforcing L.D. and highlighted judicial deference to the arbitral process and awards, barring compelling reasons for intervention.

 

Conclusion

The case underscores the complexities in disputes involving liquidated damages and delays in large-scale infrastructure projects. It highlights the necessity for clear loss quantification and the role of arbitration in resolving contractual disputes while considering the broader public interest. The High Court's decision emphasizes judicial deference to the arbitral process and awards, reinforcing the principle that courts should intervene only when necessary. This case sets a precedent for how similar disputes may be approached, balancing contractual obligations, actual losses, and public interest considerations.

  • The dispute centered on delays in completing an infrastructure project (Project G09) and the validity of the L.D. imposed by HVPNL.
  • The court upheld the arbitrator's decision to reduce the L.D. by 50%, citing HVPNL's failure to precisely quantify the losses incurred due to the delay.
  • This decision reinforces the principle of judicial deference to arbitral awards and the necessity of clear loss quantification in L.D. disputes.

BY : Fanuel Rudi

All Latest News